kitchen renovation costs: a Canadian contractor's breakdown

Kitchens are high-value jobs with a lot of moving parts. Plumbing, electrical, gas, cabinetry, countertops, tiling, flooring, appliances β€” the coordination alone can eat your margin if you have not priced properly. Here is what kitchens actually cost in Canada in 2026 and where the risk hides. All prices in CAD.

typical cost breakdown

Mid-range kitchen renovation for a typical 3-bedroom Canadian home. This assumes a full strip-out and refit, not just changing doors.

β”Œβ”€ Kitchen Cost Breakdown (CAD) ────────────────────────────────────────┐
ItemCost RangeRisk LevelNotes
Strip out & disposal$800 - $1,600LowPredictable unless asbestos is present
Cabinets (supply & install)$5,000 - $15,000MediumIKEA/stock = Low. Custom cabinetry = High.
Countertops$1,200 - $6,000Medium - HighLaminate = Low. Granite/quartz templated on-site = High.
Plumbing$900 - $2,000MediumMoving the sink location adds cost and risk
Electrical$1,200 - $2,500MediumPanel upgrade or rewire pushes this up
Gas (range, relocation)$400 - $1,200LowLicensed gas fitter required. Straightforward if no relocation.
Tiling (backsplash & floor)$1,200 - $3,200LowStandard subway tile = certain. Complex patterns = Medium.
Flooring$600 - $2,000LowLVP or vinyl. Subfloor prep can add cost.
Drywall & painting$600 - $1,200LowStraightforward. Old kitchens may need more prep.
Appliances$2,000 - $8,000Certain - LowUsually customer-purchased. Confirm before quoting.
Bin rental / waste$400 - $700CertainFixed price, book in advance

Total range for a mid-spec kitchen: $14,300 - $43,400. The huge range comes down to cabinet quality, countertop material, and how much layout change is involved. Add HST/GST on top.

where kitchens blow budgets

  • Countertops. Templated stone countertops are measured after the cabinets are installed, then fabricated off-site. If the template is wrong or the stone has a flaw, you are waiting weeks for a replacement. Mark bespoke countertops as High uncertainty.
  • Layout changes. Moving the sink means moving waste and water. Moving the range means moving gas and ventilation. Each relocation is another subtrade, another day, another point of failure. If the customer wants to move everything, your plumbing and electrical estimates should be Medium at minimum.
  • Lead times. Custom cabinets, stone countertops, and specialty appliances can take 4-10 weeks. If one item is late, your whole programme shifts. Price the risk of dead time into your quote or make sure the customer understands delays are at their cost.
  • Scope creep. "While you are here, can you move that radiator?" "Actually, can we replaster the whole room?" Kitchens attract scope creep because customers see the mess and want everything fixed at once. Have a clear scope in writing before you start.

quoting kitchens with confidence

A kitchen with stock IKEA cabinets, laminate countertops, and no layout changes is mostly Low-uncertainty work. You could quote close to your base estimate. A kitchen with custom cabinetry, quartz countertops, and a full layout redesign is packed with High-uncertainty items. Your contingency needs to reflect that.

Rate each line item honestly, run the simulation, and quote at P80. Your quote will be higher on risky jobs and tighter on simple ones β€” which is exactly how it should be.